Staging Plan Phase 1B

Phase 1 will be on Albert Street, between Phillip Street and Longwood Drive. Details are also available for Phase 1A and Phase 2.

Phase 1B

  • Transfer traffic to newly paved areas
  • Extend services to property line on long service side
  • Commission and connect watermain
  • Surface restorations and pave


Active work in south bound lanes from Phillip Street onwards.


Continued work in south bound lanes, followed by work in the north bound lanes from 460 Albert Street.


Continued work in north bound lanes.


Active work split between north and south bound lanes to Longwood Drive.