Construction Update August 21, 2020

View the full update here

If you have general questions about COVID-19 or want more information, please view the information provided by the Region of Waterloo .

If you have questions about this construction project related to the current COVID-19 pandemic, please review the information provided by the Region of Waterloo on the Construction and Road Closures page.

On Monday, August 31, 2020 (note the revised date) the Region’s contractor Navacon Construction Inc. will temporarily close King Street to eastbound traffic between Lowther Street and Bishop Street for approximately 8 weeks. One-way traffic in the westbound direction will continue to be permitted during this stage of the work. The Region will provide a signed detour for eastbound traffic (including heavy trucks) using Eagle Street, Hespeler Road and Bishop Street. View the Detour Map here.

Access to businesses and residential properties on both sides of King Street will be maintained within the closure limits, but traffic will only be permitted to travel in the westbound direction.

Progress Since Last Update:

  • General clean up in Stages 1 and 2 is nearly complete.
  • The north side of King Street in Stage 3 has been prepared and curbs have been placed.
  • Sewer connections on side streets in Stage 3 are complete.

Upcoming Work over the next few weeks:

  • Paving is scheduled next week for the first half of Stage 3 (north side of King Street).
  • Traffic will be flipped to the north side of the street and removals (asphalt, curb, rail ties) for the south side of King Street in Stage 3 (between Laurel Street and Montrose Street) will begin.

We appreciate the community's continued understanding as we complete this important work.

Every reasonable effort is being made during construction to minimize disruption and complete the work efficiently and cost effectively. We thank you for your patience and cooperation.

View the full update here for some pictures from the last two weeks

Road excavation in Stage 3

Topsoil placed in Stage 1

Connect sanitary sewer service in Stage 3

Connect catch basin in Stage 3

Install sleeves for water services in Stage 3

Place road gravel in Stage 3

Ready for sod in Stage 1

Topsoil placed in Stage 1

Ready for curb in Stage 3

Connect catch basin in Stage 3

Cutting old manhole for adjustment in Stage 3

Cut manholes ready for new tops in Stage 3

Pouring new curb in Stage 3

New curb in Stage 3

New planters filled in Stage 1