Construction Update August 7, 2020

View the full update here

If you have general questions about COVID-19 or want more information, please view the information provided by the Region of Waterloo .

If you have questions about this construction project related to the current COVID-19 pandemic, please review the information provided by the Region of Waterloo on the Construction and Road Closures page.

One lane of traffic will be maintained in each direction, similar to 2019. Between Dover Street and Laurel Street. Removal of on-street parking will be necessary, but will be for a shorter duration than in 2019. As crews finish the sidewalks, landscaping and streetlights block by block, on-street parking will be reinstated.

Between Laurel Street and Bishop Street, on-street parking will be temporarily removed within the active construction zone to allow our contractor to safely and efficiently complete their work.

Progress Since Last Update:

  • Complete paver stone installation in Stages 1 and 2
  • Street benches, garbage bins, tree grates and hanging basket installation in Stages 1 and 2

Upcoming Work over the next few weeks:

  • Continue and complete side street sewer connections
  • Clean up in Stages 1 and 2, including placing planters along the street
  • Crews will begin building the roadway with gravel to prepare for curbs in Stage 3.
  • Once the roadway is prepared curbs will be placed in Stage 3.

View the full update here for some pictures from the last two weeks

New storm sewer and sanitary sewer service installation in Stage 3

New sanitary sewer service (green pipe) installation in Stage 3

Removal of existing catch basin in Stage 3

Installation of new catch basin pipe to middle of the road in Stage 3

Installation of storm sewer with truck holding street light pole in Stage 3

New pavers installed at the library in Stage 1

Completed light poles in Stage 2

Completed light poles in Stage 1

Completed tree grate and pavers in Stage 2

Watermain stub for testing in Stage 3

Planters ready for installation in Stages 1 and 2

Share on Facebook Share on Twitter Share on Linkedin Email this link