Construction Update December 13, 2019

View the full update here

We appreciate the understanding and cooperation we have received throughout this major renewal of King Street.

Our contractor is planning to have work wrapped up by the end of next week, with the possibility of minor traffic signal work to continue through to the end of December. On-street parking is anticipated to start re-opening from Dover Street towards Lowther Street next week.

A person is stationed at Westminster Drive to provide pedestrian help while crossing King Street during the commute to and from school. Help crossing this intersection will be available until the new traffic signals are operational.

Progress since last Update:

· Curbs and asphalt are complete in both stages 1 and 2.

· Temporary asphalt has been placed on the sidewalks in preparation for winter shut-down.

Upcoming work over the next week:

· Traffic signal work has started and will continue for the next couple weeks

· Traffic is scheduled to be moved to the centre of King Street, with on-street parking will be reinstated shortly after.

Reminder: Garbage collection will be returning to regular pick-ups within the construction zone next week. A notice will be delivered to all properties reminding everyone of the normal collection guidelines.

View the full update here for some pictures from the last two weeks

Stage 2 is ready for curb

Stage 2 is ready for curb

Stage 1 new curb being placed

Stage 2 new curb being placed

Stage 2 is ready for asphalt

Stage 2 asphalt being placed

Stage 2 asphalt being placed

Stage 1 asphalt being placed

Stage 1 asphalt being placed

Stage 2 temporary asphalt sidewalks

Stage 2 temporary asphalt sidewalks