Construction Update July 26, 2019

View the full update here


Progress since last Update:

· Storm sewer installation in Phase 2 working east from Argyle Street

· Completion of service installations in phase 1

Upcoming work over the next couple of weeks:

· Storm Sewer installation working west from Lowther Street in Phase 2 for approximately 3 weeks

· Sanitary and storm service connections working west from Lowther Street in Phase 2 for approximately 3 weeks

· Starting next week crews will begin building the roadway with gravel to prepare for curbs and asphalt starting in Phase 1 (Dover Street to almost Westminster Drive)

· Once the road is prepared, curbs and asphalt will follow (Dover Street to almost Westminster Drive)

· When preparing for curb installation, crews will remove the tall metal fence and reinstall the orange safety fence

We want to remind everyone that King Street will remain open to one lane of traffic in each direction for the duration of construction. For safety reasons, on-street parking on King Street will not be permitted within the construction zone.

Sanitary Sewer and manholes being installed:

Sanitary sewer installation

Sanitary Service being stalled crossing under gas and streetlight conduits:

Sanitary service installation

Temporary paving of sidewalk:

Temporary paving of sidewalk

Installation of storm service:

Storm sewer service pipe installation

Installation of watermain at Argyle Street:

Watermain installation at Argyle Street