The underground work at the intersection of King Street and Bishop Street is continuing. It is anticipated that the north side intersection closure at Bishop Street will re-open to vehicular traffic near the end of May. Sidewalks and pedestrian access at the intersection will continue to be maintained. View detour map here.


Work completed since last update:

  • Sidewalk installation on south side of King street between Union Street and Dolph Street;
  • Watermain connections at Chestnut Street intersection and at Bishop Street intersection;
  • Electrical conduit work from Montrose Street to Lowther Street;
  • Majority of tree planting.


Work to be completed over the next 2 weeks:

  • Roadway excavation on north side of King Street between Chestnut Street and Bishop Street;
  • Sidewalk installation on south side of King Street between Dolph Street and Lowther Street, and between Union Street and Chestnut Street;
  • Landscaping behind sidewalks after sidewalk installation;
  • Curb placement on north side of King Street between Chesnut Street and Bishop Street, followed by asphalt paving.

Sidewalk Granular Base Compaction



Sidewalk Concrete Fining






Over Night Watermain Connection at Bishop Street Intersection


Watermain Construction


We appreciate the community's continued understanding as we complete this important work.

Every reasonable effort is being made during construction to minimize disruption and complete the work efficiently and cost effectively. We thank you for your patience and cooperation.

Share Construction Update - May 21, 2021 on Facebook Share Construction Update - May 21, 2021 on Twitter Share Construction Update - May 21, 2021 on Linkedin Email Construction Update - May 21, 2021 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>