Construction Update May 22, 2020

View the full update here

If you have general questions about COVID-19 or want more information, please view the information provided by the Region of Waterloo .

If you have questions about this construction project related to the current COVID-19 pandemic, please review the information provided by the Region of Waterloo on the Construction and Road Closures page.

One lane of traffic will be maintained in each direction, similar to 2019. Between Dover Street and Laurel Street, the removal of on-street parking will be necessary, but will be for a shorter duration than in 2019. As crews finish the sidewalks, landscaping and streetlights block by block, on-street parking will be reinstated.

Between Laurel Street and Bishop Street, on-street parking will be temporarily removed within the active construction zone to allow our Contractor to safely and efficiently complete their work.

Progress since the last update:

  • Tree soil cell installation continues in Stages 1 and 2.
  • Streetlight installation on the north side of King Street between Dover and Church Street
  • Majority of sidewalk in Stage 1 and 2 has been installed.
  • Removal of temporary asphalt on the north side of King Street in Stage 1 and 2.
  • Testing and commissioning of temporary watermain in Stage 3 including water service connections.
  • Asphalt removal on King Street in Stage 3

Upcoming work over the next few weeks:

  • Tree soil cell installation to continue in Stages 1 and 2.
  • Continue with street light pole installation between Dover and Lowther street.
  • Rail tie removal and concrete road base removal has started in Stage 3
  • Sanitary sewer installation to start in Stage 3 after rail tie and concrete road base has been removed.

We appreciate the community's continued understanding as we complete this important work.

View the full update here for some pictures from the last two weeks

Disconnecting the old watermain at Dolph St. N.Crew separating the King St watermain from Dolph St N

Installing new light poles in Stage 2Installing new light poles in Stage 2

Connect building in Stage 3 to temporary watermainCrews making connection to temporary watermain

Pouring concrete at the cenotaph in Stage 1Crews pouring new concrete in front of cenotaph

Electrical connections to the new street light poles in Stage 1Trench showing base of streetlight pole

Temporary watermain in Stage 3Temporary watermains laid on ground in Stage 3

Removing asphalt in Stage 3Machine removing road asphalt in Stage 3

New sidewalk in Stage 1/2New sidewalk at Cenotaph