Construction Update July 2022
Completed work to date:
- Asphalt Removal
- Temporary Water installation and Connection
- Sanitary Sewer Mainline installation
- Cellar Drain Mainline Installation
Current and Upcoming work:
- Watermain installation along with Water services (currently ongoing)
- Storm Sewer installation
- Road excavation and subgrade replacement
- Select Retaining Walls
Every reasonable effort is being made during construction to minimize disruption and complete the work efficiently and cost effectively. We thank you for your patience and cooperation.