Construction Update July 2023

The construction for Stage 1A started on June 19th from George Street to approximately Spruce Lane

The work completed was

  • necessary tree removal as well as clearing and grubbing
  • replacement of a large culvert east of George Street
  • excavation and widening out of north embankement for future sidewalk installation
  • installation of new watermain within this section
  • installation of storm sewer within this section (manhole and pipes)
  • building and compaction of road structure (Granular A, B)
  • curb and gutter installation on the north side of the road
  • installation of work/debris platform on the bridge


Anticipated next steps for Week of June 17th

  • Completion of the road base within Stage 1A (George Street to approximately Spruce Lane)
  • Paving of base asphalt within Stage 1A (George Street to approximately Spruce Lane)
  • After Stage 1A is completed, the work will switch to Stage 1B (from Riverside Drive to George Street)