Construction Update and Project Completion - 2024 season

Week of May 6th, 2024 - The contractor will begin concrete deficiency and landscape work under localized lane closures. All Accesses will remain. Traffic is able to travel east and west.

Week of May 13th, 2024 - The contractor will perform underground deficiency work at Duke Street/Church Street East. This work will be completed under a full road closure of Church Street East, from Riverside Drive to Northfield Drive. The Duke St/Church Street East intersection will be closed.

Residents living on George St/High St/Charles St, will be able to enter/exit their respective streets from the Northfield Rd side.

The closure will last for 1 week. The road will be re-opened prior to the May Long Weekend.

We have coordinated the closure with school buses and waste collection services.

Week of May 20th, 2024 - Contractor will pave the final layer of asphalt for the entire project section, i.e. from Riverside Drive to 6799 Church Street East. Pavement Markings will be applied following the paving. Paving will be performed under a full closure of the entire project stretch. The duration will last 1 day.

Residents living on George St/High St/Charles St, will be advised by the contractor to exit either east or west. There will be a period of about 2 hours when the paving will occur directly in front of George Street. During this period there will be no through traffic except for Emergency Services. This is necessary to allow the asphalt to be compacted and cooled properly and is crucial for the long term performance.

After these works, the project will be completed, with the potential of minor deficiencies being repaired.