Phase 2 Construction Update: May 15 to 19

Note: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change and residents should be prepared for unexpected changes.

The following update is for the week of May 15:

  1. Continue replacement of storm/sanitary sewers and watermain between John Street and Union Street, working southeast toward Union.

Please be advised that CN Rail is starting construction on the spurline rail tracks and may will block roadways in the neighbourhood over the next several weeks. The tentative schedule for this work is:

May 15 to 19 – Union Street East

May 23 to 26 – Moore Avenue South

May 29 to June 2 – Roger Street

For details on all road and trail closures, visit our Road, trail and sidewalk closures page.