Notice - July 11, 2022

Concrete works in Stage 1C are unfortunately still ongoing as the industry is currently undergoing concrete supply shortages across the province which is affecting all construction projects at this time.

  • Exact timing of the sidewalks at this time is unknown and residents will be notified of driveway disruptions when this work is able to occur.

In addition to the outstanding sidewalks in Stage 1C, the Contractor is also using isolated lane closures to address some deficiencies from Gingerich Road to Whiting Way.


Sanitary sewer installation is on-going at Brewery Street and heading east and due to unfavorable site conditions progress has been slower then we had hoped. Dewatering challenges with the sanitary installation is limiting production rates and prolonging the construction progress. Please be mindful that excavations will be left open at night to aid the Contractor’s production and progress, along with maintain the dewatering operations.

Motorists should speak to the Region's onsite inspector Jeremy Bieniarz (WalterFedy) at 519-465-0539 or jbieniarz@walterfedy.com regarding the best route to navigate through site as the construction operations are ongoing.

Thank you for your continued patience.