Construction Update - April 5, 2023

The Region will start this season’s construction on Weber Street North on or about April 11, and we anticipate this work will continue through late fall.


Construction area
The construction will start at the Parkside Drive intersection and move north towards the Northfield Drive intersection. We will replace underground servicing and reconstruction the road in this area. View the map for the
construction area and detours.


Closures and detours
The work at Weber Street and Parkside Drive will require a full closure of the intersection to all traffic for approximately six weeks. After that, we’ll maintain two-way traffic on Weber Street between Parkside Drive and Northfield Drive with signed routes in place. We’ll ensure pedestrian access at all times.

Construction at the Northfield Drive intersection will require additional localized short-term closures. We’ll post dates and details of this closure on this page once we have more information.


Updates
We’ll continue to post Weber Street Reconstruction Phase 2 updates on project progress, major milestones and key information such as road closure and reopening timing, and detour maps on this page. You can subscribe to this page (button on the top right side of this page) to receive notices of project updates.


We appreciate the community's continued understanding as we complete this important work. Information about this project can also be viewed on the Region’s website by going to https://www.regionofwaterloo.ca/en/living-here/construction-and-road-closures.aspx