Construction Update - August 11, 2023

Weber Street construction is ongoing with work proceeding between Parkside Drive and Northfield Drive on Weber Street.

Works conducted since last update:

  • Installation of storm sewers along Weber Street between Glen Forrest Boulevard and Northfield Drive.
  • Road excavation, curbs and sidewalk installation on south-west side of Weber Street between Glen Forrest Boulevard and Northfield Drive.
  • Installation of watermain and connections at Glen Forrest Boulevard intersection.


Works planned for August:

  • Complete all storm sewers installation.
  • Road grading, base asphalt paving and pavement markings on the south-west side of Weber Street.
  • Surface asphalt paving on Weber Street from Forwell Creek Road to Blythwood Road.
  • Start new Zone 4 and Zone 5 watermain installation at the north-east side of Weber Street.