Construction Update - August 11, 2023
Weber Street construction is ongoing with work proceeding between Parkside Drive and Northfield Drive on Weber Street.
Works conducted since last update:
- Installation of storm sewers along Weber Street between Glen Forrest Boulevard and Northfield Drive.
- Road excavation, curbs and sidewalk installation on south-west side of Weber Street between Glen Forrest Boulevard and Northfield Drive.
- Installation of watermain and connections at Glen Forrest Boulevard intersection.
Works planned for August:
- Complete all storm sewers installation.
- Road grading, base asphalt paving and pavement markings on the south-west side of Weber Street.
- Surface asphalt paving on Weber Street from Forwell Creek Road to Blythwood Road.
- Start new Zone 4 and Zone 5 watermain installation at the north-east side of Weber Street.
Share Construction Update - August 11, 2023 on Facebook
Share Construction Update - August 11, 2023 on Twitter
Share Construction Update - August 11, 2023 on Linkedin
Email Construction Update - August 11, 2023 link