Construction Update August 1, 2022

Weber Street construction is on schedule with work under construction at Cedar Creek culvert and the west side of Weber Street within construction limits.

Works being conducted since last update:

  • Completed installation of storm sewer and services between Albert Street and Dutton Drive
  • Completed base asphalt pavement and curb placement on east side of Weber Street from Belcan Place to Blythwood Road
  • Reopened two-way traffic on east side of Weber Street between Belcan Place and Blythwood Road
  • Commenced installation of sanitary sewer and services between Albert Street and Dutton Drive
  • Commenced Cedar Creek culvert replacement work

Works planned for August:

  • Complete Cedar Creek culvert replacement
  • Complete watermain installation between Albert Street and Dutton Drive
  • Commence road excavation on west side of Weber Street between Belcan Place and Blythwood Road
  • Commence watermain and underground service lead connections


Placement of Storm Manhole Storm Pipe Installation Concrete Curb Pouring Concrete Curb and Catch Basin Installation Base Asphalt Paving Base Asphalt on East side of Weber Street

Hydro Anchor Relocation for Culvert Work