Construction Update August 1, 2022
Weber Street construction is on schedule with work under construction at Cedar Creek culvert and the west side of Weber Street within construction limits.
Works being conducted since last update:
- Completed installation of storm sewer and services between Albert Street and Dutton Drive
- Completed base asphalt pavement and curb placement on east side of Weber Street from Belcan Place to Blythwood Road
- Reopened two-way traffic on east side of Weber Street between Belcan Place and Blythwood Road
- Commenced installation of sanitary sewer and services between Albert Street and Dutton Drive
- Commenced Cedar Creek culvert replacement work
Works planned for August:
- Complete Cedar Creek culvert replacement
- Complete watermain installation between Albert Street and Dutton Drive
- Commence road excavation on west side of Weber Street between Belcan Place and Blythwood Road
- Commence watermain and underground service lead connections
Share Construction Update August 1, 2022 on Facebook
Share Construction Update August 1, 2022 on Twitter
Share Construction Update August 1, 2022 on Linkedin
Email Construction Update August 1, 2022 link