Construction Update - December 22, 2023
Base asphalt and line painting work has been completed on Weber Street North including the Northfield Drive intersection. All 2023 work is now wrapped up for the winter.
In Spring 2024, the contractor will work on landscaping and minor restoration works with no major traffic impact. Surface asphalt paving will be completed during nights in Summer 2024 to minimize the impact on public. The estimated closure duration for surface asphalt is approximately 3 nights. Advance Notice will be provided to the local residents/businesses once more details on the schedule become available for this work.
Should you have any questions, please feel free to reach out to our project manager, Jason Guan at jguan@regionofwaterloo.ca
Have a wonderful holiday and happy new year!