Construction Update June 1, 2022
We have started work on the east side of Weber Street between Blythwood Road and Albert Street since late April.
Works being conducted so far:
- Sanitary sewer construction in City of Waterloo’s Easement beside 475 King Street and along Weber Street.
- Storm sewer construction in the City’s Easement and along Weber Street.
Works planned for June:
- Complete the remaining sanitary and storm sewer construction in the City’s Easement and along Weber Street.
- Start watermain construction on Weber Street.
- Start excavation and preparatory work for replacement of the Cedar Creek Culvert.
- Start constructing the Weber Street road base.