Construction Update - June 14, 2023
Weber Street construction is ongoing with Weber Street and Parkside Drive intersection reopened and work currently proceeding towards Northfield Drive on south-east side of Weber Street.
Works conducted since last update:
- Completed underground, road rebuild and most of surface works at Parkside Drive intersection
- Completed base asphalt pavement at Parkside Drive intersection
- Installed permanent traffic signals at Parkside Drive intersection
- Reopened Weber Street and Parkside Drive with two-way traffic
Works planned for June:
- Move into Stage 2: storm sewer replacement at south-east side of Weber Street towards Northfield Drive
- Remove existing watermain and implement temporary watermain between Parkside Drive and Northfield Drive
- Continue road rebuild, install new curb and sidewalk towards Northfield Drive
Information about this project is available on our EngageWR project page. Please forward any questions to Jason Guan at JGuan@regionofwaterloo.ca(External link) or at 519-575-4400 ext. 3302
Share Construction Update - June 14, 2023 on Facebook
Share Construction Update - June 14, 2023 on Twitter
Share Construction Update - June 14, 2023 on Linkedin
Email Construction Update - June 14, 2023 link