Construction Update - May 12, 2023
In mid-April we started work at the Weber Street and Parkside Drive intersection and along Weber Street towards Northfield Drive.
Works conducted so far:
- Watermain construction within Weber/Parkside intersection and along Weber Street and Parkside Drive.
- Storm sewer construction within Weber/Parkside intersection and along Weber Street.
- Existing traffic signals removal and new signal conduit installation at Weber/Parkside intersection.
- Road base construction at Weber/Parkside intersection.
Works planned for May:
- Install watermain final connections and commission the new watermain at Weber/Parkside intersection.
- Install a temporary watermain along Weber Street towards Northfield Drive.
- Continue storm sewer and road base construction along Weber Street towards Northfield Drive.
- Install curb and gutter, sidewalk, and new permanent signals at Weber/Parkside intersection.
- Pave base asphalt at Weber/Parkside intersection and reopen the road.
Information about this project is available on our EngageWR project page. Please forward any questions to Jason Guan at JGuan@regionofwaterloo.ca or at 519-575-4400 ext. 3302
Share Construction Update - May 12, 2023 on Facebook
Share Construction Update - May 12, 2023 on Twitter
Share Construction Update - May 12, 2023 on Linkedin
Email Construction Update - May 12, 2023 link