Weber Street construction is ongoing with work proceeding at Northfield Drive intersection and part of north-east side of Weber Street.

Works conducted since last update:

  • Completion of all storm sewers.
  • Installation of Zone 4 and Zone 5 watermains and connections at Northfield Drive intersection.
  • Installation of electrical parts and pole bases for permanent traffic signals at Northfield Drive intersection.

Works planned for November:

  • Complete all remaining watermain work.
  • Road rebuild, curb and sidewalk on the north-east side of Weber Street.
  • Install permanent traffic signals at Northfield Drive intersection.
  • Pave base asphalt and reopen the road.