Construction Update November 8, 2022

Weber Street has been re-opened to two-way traffic. Construction is reaching the final stage of the 2022 season with boulevard work currently proceeding between Dutton Drive and Blythwood Road.


Work conducted since last update:

  • Completed all underground facilities installation including watermain, sanitary and storm sewers, and Cedar Creek Culvert
  • Completed road base and curb installation
  • Completed permanent traffic signals at Albert Street intersection
  • Paved base asphalt and reopen Weber Street to two-way traffic


Works planned for November:

  • Complete remaining Armour stone wingwall installation at Cedar Creek
  • Complete multi-use trail and concrete sidewalk
  • Landscaping work
  • Re-open Weber Street to all lanes of traffic
  • Shut down operations for the winter (late November or early December)


Coring Tie-in Hole on Culvert Box
Watermain Connection to Albert St Median Pouring


Color Concrete Boulevard Installation


Electric Conduit Installation



Signal Pole Installation



Weber St Reopen