Construction Update November 8, 2022
Weber Street has been re-opened to two-way traffic. Construction is reaching the final stage of the 2022 season with boulevard work currently proceeding between Dutton Drive and Blythwood Road.
Work conducted since last update:
- Completed all underground facilities installation including watermain, sanitary and storm sewers, and Cedar Creek Culvert
- Completed road base and curb installation
- Completed permanent traffic signals at Albert Street intersection
- Paved base asphalt and reopen Weber Street to two-way traffic
Works planned for November:
- Complete remaining Armour stone wingwall installation at Cedar Creek
- Complete multi-use trail and concrete sidewalk
- Landscaping work
- Re-open Weber Street to all lanes of traffic
- Shut down operations for the winter (late November or early December)
Share Construction Update November 8, 2022 on Facebook
Share Construction Update November 8, 2022 on Twitter
Share Construction Update November 8, 2022 on Linkedin
Email Construction Update November 8, 2022 link