Construction Update October 3, 2022

Weber Street construction is ongoing with work currently proceeding between Dutton Drive and Albert Street and at Cedar Creek Culvert.


Work conducted since last update:


  • Installed new box culvert at Cedar Creek
  • Installed watermain between Albert Street and Dutton Drive
  • Completed road base and installed concrete curb from Blythwood Road to Belcan Place
  • Poured colored concrete boulevard on east side of Weber Street


Works planned for October:


  • Complete remaining Cedar Creek culvert works
  • Complete road base and concrete curb from Belcan Place to Dutton Drive
  • Complete multi-use trail on east side of Weber Street
  • Install permanent traffic signal at Albert Street intersection
  • Pave base asphalt and reopen Weber Street to two-way traffic



Culvert box installation

Waterproof installationProtection board installation

Position box pieces under live hydro wire

Sanitary manhole installation

Sanitary sewer installation on Weber St

Utility supporting during excavation


Concrete curb & Colored boulevard installation