Weber Street construction is ongoing with work currently proceeding between Dutton Drive and Albert Street and at Cedar Creek Culvert.


Work conducted since last update:


  • Installed sanitary sewer between Albert Street and Dutton Drive
  • Installed storm sewer and services between Albert Street and Dutton Drive
  • Installed watermain from Blythwood Drive to Albert Street
  • Poured Cedar Creek culvert working slab and installed 2/3 of box culvert sections


Works planned for September:


  • Continuing with Cedar Creek culvert works
  • Complete watermain between Albert Street and Dutton Drive
  • Complete all road base within construction limits
  • Install concrete curb
  • Pave base asphalt and reopen Weber Street to two-way traffic (subject to timing of completion of Cedar Creek culvert works)