Weber Street construction is moving to watermain replacement stage with work proceeding between Parkside Drive and Northfield Drive on north-east side of Weber Street.
Works conducted since last update:
- Completion of all storm sewers installation.
- Completion of road excavation, curbs and sidewalk installation on south-west side of Weber Street.
- Paved base asphalt on south-west side of Weber Street and flipped traffic.
- Paved surface asphalt on Weber Street from Forwell Creek Road to Blythwood Road.
Works planned for September:
- Commencement of new dual watermain installation on north-east side of Weber Street.
- East half Weber St/Northfield Dr intersection closure for new watermain construction. Detour map can be found here.
- Road excavation, curb and sidewalk installation on north-east side of Weber Street.
- Road grading on north-east side of Weber Street.
Share Construction Update - September 8, 2023 on Facebook
Share Construction Update - September 8, 2023 on Twitter
Share Construction Update - September 8, 2023 on Linkedin
Email Construction Update - September 8, 2023 link