Construction Update - September 8, 2023

Weber Street construction is moving to watermain replacement stage with work proceeding between Parkside Drive and Northfield Drive on north-east side of Weber Street.


Works conducted since last update:

  • Completion of all storm sewers installation.
  • Completion of road excavation, curbs and sidewalk installation on south-west side of Weber Street.
  • Paved base asphalt on south-west side of Weber Street and flipped traffic.
  • Paved surface asphalt on Weber Street from Forwell Creek Road to Blythwood Road.


Works planned for September:

  • Commencement of new dual watermain installation on north-east side of Weber Street.
  • East half Weber St/Northfield Dr intersection closure for new watermain construction. Detour map can be found here.
  • Road excavation, curb and sidewalk installation on north-east side of Weber Street.
  • Road grading on north-east side of Weber Street.