As part of the City of Kitchener’s ongoing efforts to provide consistent and reliable service, we have scheduled road and sewer improvements in your neighbourhood on the street(s) listed above.

These improvements are scheduled to begin, around, April 8, 2024, with an estimated completion date on or around November 28, 2025.

The following is a brief list of specific improvements being considered:

  • Upgrade the existing storm sewer, sanitary sewer and water mains, including additional hydrants as required.
  • Replace existing sanitary and water services from the new mains to the property line.
  • Curb and gutter, and sidewalks will be installed.
  • Upgrade the asphalt roadway.
  • Replace all driveway ramp entrances in concrete.
  • Replace existing on-road cycle lanes with protected cycle tracks
  • Replace existing on-road parking lanes with protected parking lanes
  • Changes to on-road parking at Kingsdale Community Centre

These improvements will upgrade the existing, deteriorated underground services and above-ground surface features, in order to prevent future system failure. The project will be funded through utility user fees and will not result in a direct charge to the homeowner.

How you may be affected

This project will occur in five phases:

  • Phase 1 – North End to Franklin Street South is scheduled for April 2024 to July 2024
  • Phase 2 – Franklin Street South to Eighth Avenue is scheduled for July 2024 to August 2024
  • Phase 3 – Eighth Avenue to Fairlawn Road is scheduled for September 2024 to December 2024 (potential work during spring/summer of 2025)
  • Phase 4 – Completion of cycle track along the north side of Wilson Avenue from North End to Fairlawn Avenue (2025)
  • Phase 5 – Watermain crossing of Montgomery Creek is scheduled for May 2024 to June 2024

Important information

Learn more about the project and how construction may affect you.