Staging Plan Phase 2

Phase 2 will be on Albert Street, between Columbia Street and Phillip Street. Details are also available for Phase 1A and Phase 1B.

Phase 2

  • Install islands, separator curbs, line painting etc.
  • Remove existing surface features
  • Install watermain up to connection limits
  • Surface restorations, curbs, separator curbs, pedestrian islands and paving

During this phase Albert Street will be closed between Columbia Street to Phillip Street for through traffic, although local traffic access will be available at all times.

Phase 2 will take approximately 61 days.


Active work in both north and south bound lanes from Columbia Street West onwards.


Continued active work in both lanes until Phillip Street.


Active work in the south bound lanes followed by work in north bound lanes.


Continued work in north bound lanes followed by split work between north bound and south bound lanes to Longwood Drive.