Construction Update April 24, 2020

View the full update here

If you have general questions about COVID-19 or want more information, please view the information provided by the Region of Waterloo .

If you have questions about this construction project related to the current COVID-19 pandemic, please review the information provided by the Region of Waterloo on the Construction and Road Closures page.

One lane of traffic will be maintained in each direction, similar to 2019. Between Dover Street and Laurel Street, the removal of on-street parking will be necessary, but will be for a shorter duration than in 2019. As crews finish the sidewalks, landscaping and streetlights block by block, on-street parking will be reinstated.

Between Laurel Street and Bishop Street, on-street parking will be temporarily removed within the active construction zone to allow our Contractor to safely and efficiently complete their work.

Progress Since Last Update:

  • Concrete removal and temporary asphalt removals has been completed in Stages 1 and 2
  • Tree soil cell installation on the North side of King Street
  • Preparation and pouring of curb in Stage 1 around the intersections
  • Streetlight installations in Stages 1 and 2
  • Assembly of temporary watermain in Stage 3

Upcoming Work over the next few weeks:

  • Tree soil cell installation to continue in Stages 1 and 2
  • Curb installation in Stage 2
  • Sidewalk installation in Stages 1 and 2
  • Streetlight installations in Stages 1 and 2
  • Testing and commissioning of watermain in Stage 3
  • Asphalt removal on the East side of King Street in Stage 3

We appreciate the community's continued understanding as we complete this important work.

View the full update here for some pictures from the last two weeks

Removal of temporary asphalt sidewalks and existing concrete sidewalksexisting sidewalk removal

Installation of a tree soil cell systemtree soil cell system installation

Installation of a tree soil cell systemtree soil cell system installation

Removal of existing streetlight polestruck removing old streetlight poles

Installation of new streetlight polestruck installing new streetlight poles

Installing electrical conduits (grey pipe) for streetlightstrench with electrical conduits

Installing concrete curbmachine pouring concrete curb

Pouring sidewalk in Stage 1forms ready for concrete sidewalk pour

Sidewalk complete at Waterloo Streetnew sidewalk at Waterloo Street

Share Construction Update April 24, 2020 on Facebook Share Construction Update April 24, 2020 on Twitter Share Construction Update April 24, 2020 on Linkedin Email Construction Update April 24, 2020 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>