Progress since last update:
· The roadway in Phase 1 has been prepared with gravel and is ready for curb placement between Dover Street to almost Westminster Drive.
· Storm sewer installation east of Lowther Street has started
Upcoming work over the next couple of weeks:
· Continue storm sewer installation working west from Lowther Street in Phase 2
· Start installing sanitary and storm sewer service laterals working west from Lowther Street in Phase 2
· Start placement of curb in Phase 1 (Dover Street to almost Westminster Drive)
· Start placement of asphalt in Phase 1 (Dover Street to almost Westminster Drive)
· Start placement of underground conduits for new streetlights
We want to remind everyone that King Street will remain open to one lane of traffic in each direction for the duration of construction. For safety reasons, on-street parking on King Street will not be permitted within the construction zone.
View the full update here for some pictures from the last 2 weeks:
Installation of sanitary sewer lateral service under gas (yellow pipe), streetlight conduit (grey pipe) and temporary watermain (blue pipe)
Start storm sewer installation in front of Giant Tiger
Installation of storm manhole and double catch basin
Installation of watermain to connect to Waterloo Street
Start excavation of road near Westminster Drive
Road excavation in front of Idea Exchange
Placement of road gravel complete