Keats Way: Tributary Channel to Clair Creek restoration & storm sewer bypass

Share on Facebook Share on Twitter Share on Linkedin Email this link

Keats Way Storm Sewer Bypass Installation (Keats/Karen Walk to Clair Creek) and Restoration of Tributary Channel to Clair Creek

In 2020 the City of Waterloo completed the Stormwater Management (SWM) Master Plan. As part of this process a tributary channel to Clair Creek beginning near Keats Way and Keats Walk and ending at Clair Creek near McDougall Road was identified as a priority area for erosion control and bank stabilization, especially with respect to failing gabion walls (wire mesh baskets filled with rocks). The rehabilitation and stabilization of the channel’s bank will reduce the risk of further erosion and bank failure that would result in flooding and damage to private property in this area.

In addition to the need for bank stabilization, the SWM Master Plan also identified a need for a new storm sewer along Keats Way that will allow a portion of the stormwater flow to bypass the channel and discharge directly into Clair Creek at the concrete box culvert that conveys Clair Creek under Keats Way. This bypass sewer will lessen the peak flows of stormwater in the tributary channel that has resulted in frequent rear yard flooding of adjacent properties.

If you have any questions our project team is happy to take them.

Keats Way Storm Sewer Bypass Installation (Keats/Karen Walk to Clair Creek) and Restoration of Tributary Channel to Clair Creek

In 2020 the City of Waterloo completed the Stormwater Management (SWM) Master Plan. As part of this process a tributary channel to Clair Creek beginning near Keats Way and Keats Walk and ending at Clair Creek near McDougall Road was identified as a priority area for erosion control and bank stabilization, especially with respect to failing gabion walls (wire mesh baskets filled with rocks). The rehabilitation and stabilization of the channel’s bank will reduce the risk of further erosion and bank failure that would result in flooding and damage to private property in this area.

In addition to the need for bank stabilization, the SWM Master Plan also identified a need for a new storm sewer along Keats Way that will allow a portion of the stormwater flow to bypass the channel and discharge directly into Clair Creek at the concrete box culvert that conveys Clair Creek under Keats Way. This bypass sewer will lessen the peak flows of stormwater in the tributary channel that has resulted in frequent rear yard flooding of adjacent properties.

If you have any questions our project team is happy to take them.

  • Construction Update Dec. 8, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The curbs and sidewalks have been restored and roadway has been paved. Line painting is to be completed on Saturday December 9, 2023. Although the roadway is open to local traffic, the road will need to remain closed to through traffic a little longer before it can be re-opened. The following is a rough schedule for the week of December 11,2023:

    Monday: Landscape restoration (topsoil and sod of disturbed boulevard areas).

    Tuesday/Wednesday: No significant work expected. Possible minor cleanup, completion of landscape restoration not completed on Monday, etc.

    Thursday: Use of crane to install low profile lid on maintenance hole at corner of Keats Walk and Keats Way.

    Friday: Back filling soil around maintenance hole and final cleanup

    The roadway will be re-opened following final cleanup, which is expected to be complete by end of day Friday the 15, 2023. The re-opening date is contingent upon the delivery date of the low profile lid for the maintenance hole. The current installation date is based on the delivery date provided by the precast concrete manufacturer but is subject to change.

    Please note that due to unexpected conflicts with natural gas mains at the corner of Keats Way and Karen Walk, some components of the bypass sewer design could not be installed this fall. These components are not critical to the functioning of the storm sewer bypass but would be expected to improve performance. These components may be installed in 2024 following adjustment of natural gas infrastructure. Schedule to be confirmed.

    Replacement of all malfunctioning water valves has also been completed. Any water shutdowns going forward would be the result of an unexpected break of the watermain.

  • Construction Update November 9, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Due to some unforeseen conditions on-site, the contractor was not able to install the final pieces of the storm bypass sewer. Additional concrete culvert/sewer pieces need to be manufactured. As a result, the schedule has been changed to complete other minor works as well as address the issue of broken water valves while we wait for the additional culvert/sewer pieces to be made.

    Forecast work for the next two weeks.

    1. November 9 – Complete minor concrete works on new storm bypass sewer at Keats/Karen Walk and Keats Way.
    2. Date TBD – Complete concrete encasement of underground hydro crossing Keats Way at Keats Way Place. Residents of Keats Way Place should expect some disruptions getting in and out of cul-de-sac due to work vehicles in the vicinity. Please speak to one of the workers on-site if you’re unsure about how to access Keats Way Place by vehicle. The work is to be completed under the supervision of Enova Power and date is TBD in consultation with Enova.
    3. November 13 – Replace valve on watermain near Keats Way and McDougall. Water shutdown and repair will start at 4:00pm to avoid disruptions to Keats Way Public School. Residents affected by shutdown will receive notice in the mail.
    4. November 14 – Replace valve on watermain in intersection of Keats Walk and Keats Way. Residents affected by shutdown will be provided with notices in the mail.
    5. Week of November 20 – Receive final culvert/sewer pieces. Crane in final pieces of storm bypass sewer. Begin preparing for curbs and asphalt.

    Although the contractor will be repairing two valves within projects limits, there is still one more valve on McDougall south of Keats Way that City will need to replace following construction. Residents affected by water shutdowns from the repair next week should not be affected by the valve repair on McDougall following construction.

  • Halloween Construction Update October 31

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    This update provides information about an upcoming water shutoff for local residents and a schedule for upcoming work.

    Water Shutdown

    An unexpected issue encountered on-site will result in the need for one final planned water shut off as part of this project. The water shutoff is anticipated to affect residents of Keats Walk, Keats Way Place and Keats Way Public School. The shut off is currently planned to start at 6 p.m. Wednesday, November 1, 2023 in order to avoid shutting off water to Keats Way Public School while the school is open. Notices will be delivered to the mailbox of affected residents.

    Please note there are several valves in the neighbourhood that have been discovered to be non-operable as a result of this project and City of Waterloo utilities is planning to replace these valves following completion of construction. This will result in additional water shut offs to residents in the area at a later date.

    Construction Update and Local Access

    Work for the next two weeks will primarily occur near the intersection of Keats Way and Keats/Karen Walk. Residents of Keats Way Place will access their cul-de-sac via Keats Way and McDougall. Residents of Keats Walk will access their cul-de-sac via Keats Way and Amos. There will be more construction materials and equipment in the area.

    Forecast work for the next two weeks (Oct 30 to Nov 10).

    1. Continue installing bypass sewer sections up to intersection of Keats Way and Keats Walk.
    2. Adjust watermain on Keats Way near Keats Walk. Currently planned for Wednesday November 1, water shut off starting at 6 p.m.
    3. Use a crane to install “flow split” structure near Keats Way and Keats Walk. Currently planned for Monday, November 6, 2023.
    4. Install new storm sewer connecting Karen Walk to new bypass storm sewer.
    5. Rebuild granular road structure.
  • Construction Update October 23 – Closure of Keats Way and Karen/Keats Walk

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Starting on Monday October 30th, the construction work will close the intersection of Keats Way and Karen/Keats Walk to all but local vehicle traffic for the remainder of the project. Simultaneous with this closure, the Region of Waterloo is closing Erb Street West from Amos to University for one week.

    During this time, residents of Keats Walk should still have access in and out of the cul-de-sac via Keats Way to the west, however there will be frequent construction traffic in the area and materials stored along the roadway, so please do not hesitate to ask one of the workers on-site about access if you’re unsure. Residents of Keats Way Place will have access to the east towards McDougall.

    The current schedule has the intersection of Keats Way and McDougall being paved with asphalt on Saturday October 28th. Residents of McDougall between Erb and Keats Way will be able to access their street from Keats Way via the repaved intersection of Keats Way and McDougall. If the intersection is not able to be paved due to weather, it will be re-opened on gravel.

    The sidewalk on the north side of Keats Way, immediately east of Keats Walk, will be closed. Additionally, the roadway crossing of Karen Walk at Keats Way will be blocked. The crossing guard will be relocated to Keats Way and McDougall for the remainder of the project. For children walking to Keats Way Public School, please try to adhere to the following:

    1. For students approaching from the west, cross to the south side of Keats Way at Amos Avenue using the crossing guard there. At Karen Walk, use the west side sidewalk to walk south, then cross Karen Walk once past the construction zone.
    2. For students approaching from the east, or who live on Keats Way Place, use the relocated crossing guard at McDougall to cross to the south side of Keats Way.

    Due to the closure of Erb Street West from Amos to University during the week of the 30th, the current detour along Fischer-Hallman-Erb-University will be altered such that motorists will stay on Fischer-Hallman or University Avenue until they intersect.

  • Construction Update October 19 (watermain break)

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    A watermain break has occurred at the intersection of Keats Way and Keats Way Place. The break is not directly related to any construction work occurring on-site. The City has provided hard copy notices to residents of Keats Way Place regarding the schedule for the repair of the watermain. Water will be maintained to Keats Way Public School until the end of after school programming, the repair is scheduled to begin at approximately 6 p.m.

    Residents of Keats Way Place are advised to move their vehicles to nearby streets in advance of the repair work, which will block the intersection. Community enforcement has been made aware of the situation and will not be ticketing residents who are parked overnight or exceed the normal parking limit during the day, on the following streets: McDougall, Keats Walk, Karen Walk and Helene Crescent. Residents are still required to follow all other regular restrictions such as not parking in the opposite direction of traffic, not parking within 3 metres of a fire hydrant, not parking within 1.5 metres of a driveway entrance, etc. For more information on regular parking restrictions please review the City’s traffic and parking bylaw on the City’s website.

    Parking enforcement is a manual process and mistakes are occasionally made. If you receive a ticket for parking overnight or longer than three hours please contact the project manager with a copy of the ticket to determine if it can be cancelled.

  • Construction Update September 26

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change and residents should be prepared for unexpected changes.

    Upcoming work:

    1. Lowering of watermain to remove conflicts with storm bypass sewer
    2. Adjusting third party utilities (e.g. Rogers, Bell, hydro, gas) to remove conflicts with storm bypass

    During some shutdowns, your water may be turned off. Residents affects by water shutdowns will be notified by a letter from the contractor, so please keep an eye out for that letter in your mailbox. Some tips to alleviate the inconvenience of a shutdown:

    1. Fill up pitchers of water for drinking and put them in the fridge.
    2. Fill up sinks with water in advance for hand washing or dishwashing.
    3. Fill up buckets or a bath tub with water that can be used for flushing toilets. Toilets can be flushed by filling up the tank at the back of the toilet after a flush, using the water from the buckets and bath tub. Tank-less toilets can be flushed by quickly dumping the water from the bucket into the bowl. Be careful not to splash!

    As of this update, residents of Keats Way Place have access during working hours via Keats Way and McDougall. The means of access may vary from day to day based on the location of work for that day so please be aware and take your cues from the layout of the pylons and direction from workers on-site.

  • Keats Way construction begins Monday September 18

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Construction on the Keats Way storm bypass is scheduled to begin on Monday September 18. Steed & Evans will be mobilizing materials and equipment to site and setting up barricades to delineate the construction zone.

    Limits of Work and Phasing

    The project involves installing a new bypass storm sewer from the Clair Creek culvert (just east of McDougall) to Keats/Karen Walk. The first phase of the project involves closing Keats Way from just east of the Clair Creek culvert to the east side of the intersection of Keats Way and Keats/Karen Walk. The intersection of Keats Way and Keats/Karen Walk will remain open for the first phase of the project. Once the installation of the sewer approaches the intersection, it will be fully closed to vehicle traffic.

    Local Access

    Sidewalks on both sides of Keats Way are to remain open during construction, with one exception towards the end of the project. The sidewalk on the north side of Keats Way will be blocked towards the end of the project for the installation of the bypass sewer. When this occurs, pedestrians will be advised to use the sidewalk on the south side.

    Although the roadway will be closed, local vehicle traffic to the cul-de-sacs of Keats Walk and Keats Way Place will be maintained. The bypass storm sewer is to be installed under the eastbound lane of traffic. For the majority of the project, access is anticipated to be maintained via the westbound lane of traffic on Keats Way. However, there will be times where the means of local access for vehicles changes due to the complete closure of the road and alternate routes are required. Please be prepared to follow local directions.

    Pedestrian and School Bus Access to Keatsway Public School

    Sidewalks on Keats Way are to be kept open during construction, with one exception. A small section of the north side sidewalk will be closed towards the end of construction. Children walking to school can continue to use the sidewalks on Keats Way.

    The school crossing guard at the pedestrian refuge island near Keats Way Place will be temporarily relocated to Keats Way and Keats/Karen Walk for the first phase of construction, when the intersection of Keats Way and Karen Walk is open. Once the intersection is fully closed, the crossing guard will be temporarily relocated to Keats Way and McDougall. Once construction is complete, the guard will return to a rebuilt pedestrian refuge island near Keats Way Place.

    The pickup and drop-off location for school buses will be relocated to Karen Walk, adjacent the school staff parking lot south of Keats Way and north of the parking lot entrance. This will continue as long as the intersection of Keats Way and Karen Walk remains open as buses will be able to exit westbound onto Keats Way. Towards the end of construction, when the intersection is closed to traffic, the pickup/drop-off location will move to Karen Walk south of the entrance to the school parking lot. This will allow school buses to exit via Helene Crescent.

    Parents who pickup and drop-off children at the start and end of the school day are advised to park further south on Karen Walk or further away on Helene Crescent in order to ensure there is space for school bus parking and to be able to turn at the intersection of Karen Walk and Helene Crescent.

    Grand River Transit Re-routing

    GRT Route 29 Keats-University will be diverted for the duration of construction. GRT has indicated that the bus will be re-routed via Amos-Erb-University. Please check for detours on Grand River Transit’s detours webpage:

    https://www.grt.ca/en/schedules-maps/detours.aspx

    Waste Removal on Cul-de-sacs

    Residents of Keats Walk and Keats Way Place are advised that they are to put their waste out weekly, as normal. The contractor will work with the waste pickup services to get access to the cul-de-sacs on waste day. If the cul-de-sac cannot be accessed by the vehicle, the contractor is responsible for ensuring that all bags and bins are moved to an accessible location for pickup. The contractor will return the bins to the roadside in front of your house at the end of the day, please put your address on bins.

    Parcel and Medical Supply Delivery Service

    Parcel delivery may be affected during construction. Frequently, parcel delivery can be maintained during construction, however the decision to make a delivery is typically up to the individual delivery driver. The City does not have any influence as to whether a driver deems it safe to make a delivery. It’s advised that residents minimize the use of delivery service during construction to avoid the potential for parcels to be held up.

    Residents who receive deliveries of essential medical supplies should contact the City’s project manager to discuss. If the contractor is aware of the timing of such deliveries they can frequently assist in making the delivery, if needed.

    Telecommunication Services

    The Keats Way storm bypass project won’t involve many crossings of telecommunication (i.e. Bell, Rogers) lines, however there will be some crossings. It is possible that this work could cut a telecom cable, especially if it’s not well located.

    In the event that telecom services are cut off, please inform one of the workers on-site followed by your telecom provider. The contractor will contact the telecom and coordinate the repair, however previous experience has shown that telecoms will expedite the repair if individual customers complain directly.

    Residents who work from home or otherwise rely on telecom services such as cable and internet during the day are advised to have a contingency plan in place in the event that a telecom cable is severed. An example of a contingency for those who require internet to work from home would be to tether your work station to a WiFi hotspot created using a cell phone in the short term, and moving your work station to another home or location with public WiFi to minimize the possibility of data overage charges. It is advised that employers are informed of the upcoming construction in advance.

  • Keats Way construction to begin in September

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Notice of Construction for Keats Way Storm Bypass Project

    This is to provide notice that construction on Keats Way for the Storm Bypass is tentatively scheduled to start mid-September 2023. An exact date is not yet available and is dependent on timing for delivery of the storm sewer pipe that will be installed. Steed and Evans Limited has been retained by the City as the general contractor to complete the construction for this project. The City’s engineering consultant, Aecom, will have a full-time inspector on-site to oversee the work of the contractor and liaise with neighbourhood residents. Once a tentative date is available it will be posted on this page, and additional details of what to expect during construction will also be provided once available.

    We now expect that the Clair Creek channel rehabilitation portion of the project will be completed in 2024, once construction on the sewer bypass is complete and can be used as a diversion for storm water during construction.

  • Keats Way storm sewer bypass update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Work on the Keats Way bypass storm sewer continues to progress towards construction. An application for approval for both the sewer bypass project and tributary channel rehabilitation project was sent to the Grand River Conservation Authority. Provided there are no concerns, approval is anticipated within the next 3-5 weeks.

    Concurrently with the application for approval, the City will complete an environmental investigation along Keats Way and the tributary channel. This investigation is required by the new Excess Soil regulation. The investigation will involve the use of a drilling rig to collect soil samples along Keats Way, and hand held soil sampling equipment to collect samples along the tributary channel. This investigation is anticipated to be completed over the course of one day. The investigation is anticipated to be completed in the next 2-3 weeks, pending availability of drilling contractors and following receipt of underground utility locates.

    Pending receipt of approvals, the anticipated construction schedule is:

    Start Date: late May/early June 2023

    Completion Date: late summer 2023

    Tributary Channel Rehabilitation

    Start Date: fall 2023 or mid-July 2024

    Completion Date: late fall 2023 or late summer 2024

    The tributary channel rehabilitation construction will be completed following the storm sewer bypass. Construction may need to be delayed to 2024 if there is insufficient time to complete the project in 2023.

    Should you have any concerns or should you require any additional information you may submit submit them via the Questions tab at anytime, or directly email one of the members of the Project Team.

  • Neighbourhood meeting follow-up

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Thank you to everyone who was able to attend our neighbourhood meeting on December 1. If you were unable to attend or are looking for follow-up information, we have added some additional files to this project page. A reminder that the City lead for this project is now Gavin Vermeer, and he is the main point of contact moving forward. Additional project information now available includes:

    • the meeting presentation is available for anyone unable to attend
    • a frequently asked questions section with questions from the meeting
    • the technical drawings, including floodplain and tree removals, are available in the Document Library section

    The technical drawings include:

    If you are unable to access any of these files and require this information in another format, please let Gavin know.