Contractor introduction, parking and pre-condition survey

The City of Kitchener has Sierra Infrastructure under contract for the reconstruction work on Wayne Drive from Conway Drive to Kenora Drive. Construction is scheduled to start on/or about March 5, 2024, with an anticipated completion on/or about July 26, 2024.

As the City Project Manager, I am a key point of contact; my contact information has been provided in the contact list on the next page. A Construction Inspector will be on site daily while the contractor is working. Should you have any questions or concerns while the work is in progress the Construction Inspector can be identified by the white hardhat and can be approached at any time. Should you experience an after-hours emergency, please contact the 24-hour Contact Centre at 519-741-2345.

The Contractor will start the project with the setup of their temporary watermain and by completing the pre-condition inspection.

Pre-condition inspection of structures

On heavy construction projects, it is the City of Kitchener’s standard practice to offer to inspect any buildings that might be affected by construction activities before construction starts. If during or after construction residents/tenants experience any concerns with their property, the information from the pre-construction inspection will prove very helpful in quickly and accurately resolving any claims, should they arise.

The pre-condition survey will be conducted by Englobe. This includes inspection of the interior and exterior of each property to document the existing condition prior to construction. In large high-rise apartment buildings, the ground floor area will be inspected, but the individual apartment units above will not be inspected.

We appreciate that some tenants/residents may not want a pre-condition survey of their home and we would like to stress that you are under no obligation to do so. Should this be the case, please advise the representative when they call.

How to book an appointment

Appointments will be available from March 11 to April 5, 2024.

The pre-construction condition survey is similar to a building inspection and will involve an Englobe Technician recording the existing conditions of the interior and exterior of your building and surrounding property using video cameras. The technician will take approximately one hour to complete the survey depending on the size of your building(s).

For more information or to book an appointment, contact Rima at Englobe (rima.peters@englobecorp.com or 1-877-300-4800 ext. 620). Please reference project "02302802 – Conway and Wayne Phase 3"

How you may be affected by construction

You will likely feel some vibrations during the routine operation of construction equipment; however, studies have shown that these vibrations are much less severe than the vibration level likely to cause structural damage. We do recommend that you remove light, fragile or delicate objects from shelves when construction activity is taking place adjacent to your property.

Should you experience any problems during construction, please contact me immediately and I’ll address or direct your concern to the contractor if needed. If immediate action is needed, such as an issue with your services and City Staff or Representatives are not immediately available, you are welcome to contact the contractor directly.

Should situations arise during or after this construction project, the following contact information and telephone numbers are provided for your convenience.

On street parking

During reconstruction, temporary parking permits will be issued to displaced residents to allow on-street parking when needed. The permits will list streets for parking options as you will be permitted to park longer than 3 hours and overnight. Permits are to be displayed on the dash of your vehicle. Ensure that your vehicle is parked in permitted areas only and that you do not interfere with any construction operations. We communicate with the Bylaw Enforcement team to ensure residents displaced by construction are noted, although illegal parking and/or safety related issues will continue to be enforced. If you require parking enforcement, please contact 519-741-2345. If you have any inquiries, please speak to the site inspector for further direction.

If you would like to receive updates for this project as they become available, please subscribe and you will be added to the email list for updates on this project.

City of Kitchener Project Manager

Rob Trussler – 519-897-2816

Contractor – Sierra Infrastructure

Brandon Shaw – 519-755-9710

Corporate Contact Centre (24 hour)

519-741-2345

We appreciate your patience and understanding during this project.

Share Contractor introduction, parking and pre-condition survey on Facebook Share Contractor introduction, parking and pre-condition survey on Twitter Share Contractor introduction, parking and pre-condition survey on Linkedin Email Contractor introduction, parking and pre-condition survey link