Dodge Drive Trunk Sanitary Sewer

Share Dodge Drive Trunk Sanitary Sewer on Facebook Share Dodge Drive Trunk Sanitary Sewer on Twitter Share Dodge Drive Trunk Sanitary Sewer on Linkedin Email Dodge Drive Trunk Sanitary Sewer link

What's happening?

We are doing construction on Dodge Dr. to install a new trunk sanitary sewer. This will affect garbage pickup for residents who live on this street and we may need to close the street for a period of time.

Please read the FAQ and the Information Package for more details about how this construction may affect you. Subscribe to get project updates by using the button at the top right corner.

Project Scope

The Dodge Drive Trunk Sanitary Sewer project for this street will include:

  • Trenchless installation of trunk sanitary sewer,
  • Installation of local sanitary services (where requested),
  • Culvert replacement,
  • Reinstatement of tar and chip asphalt.

Proposed Schedule

The anticipated start date of construction is September 8, 2021. The contractor will mobilize to the site the week of August 30th. Mobilizing involves setting up site trailers, fencing, equipment and materials.

The underground works has been completed. The final top coat of tar and chip asphalt will be installed in the spring of 2024.

What's happening?

We are doing construction on Dodge Dr. to install a new trunk sanitary sewer. This will affect garbage pickup for residents who live on this street and we may need to close the street for a period of time.

Please read the FAQ and the Information Package for more details about how this construction may affect you. Subscribe to get project updates by using the button at the top right corner.

Project Scope

The Dodge Drive Trunk Sanitary Sewer project for this street will include:

  • Trenchless installation of trunk sanitary sewer,
  • Installation of local sanitary services (where requested),
  • Culvert replacement,
  • Reinstatement of tar and chip asphalt.

Proposed Schedule

The anticipated start date of construction is September 8, 2021. The contractor will mobilize to the site the week of August 30th. Mobilizing involves setting up site trailers, fencing, equipment and materials.

The underground works has been completed. The final top coat of tar and chip asphalt will be installed in the spring of 2024.

  • May 2024 update

    Share May 2024 update on Facebook Share May 2024 update on Twitter Share May 2024 update on Linkedin Email May 2024 update link

    Please be advised the city’s hired contractor, Earth Boring Ltd has two work items to complete on Dodge Drive this spring.

    Item 1: Maintenance hole repair between 238 Dodge Dr. and 246 Dodge Dr.

    To complete this work, the contractor, Earth Boring Ltd, will have to close this street to through traffic and remove a section of the road for approximately one week on Dodge drive between 238 and 246 Dodge. These repairs are scheduled to begin, on or about, Wednesday May 15, 2024 (weather permitting) and expected to take approximately one week.

    During the road closure properties can access their driveways as follows:

    • Properties located West of #246 Dodge Drive can access their driveways via West limit of Dodge Drive
    • Properties located East of #238 Dodge Drive can access their driveways via East limit of Dodge Drive.

    Map of work area 1


    Item 2: Double surface treatment of Dodge Drive (full limits)

    The double surface treatment of the roadway operation will follow the maintenance hole repair work and is anticipated to occur the week of May 21. The duration of this work will take one full working day to complete. This is a moving operation and there will be numerous heavy construction equipment onsite.

    Access to properties will be maintained during this operation but note that there may be short to medium term duration delays for access. Flaggers will be onsite to help direct traffic. Please drive slowly and safely through the work zone.

    Map of work area 2


    What to expect during construction

    Work Hours

    Work will take place from 7 a.m. up to 7 p.m., Monday to Friday. Work is not planned during the long weekend / Victoria Day stat holiday.

    Construction noise

    You may experience intermittent noise and vibration during construction (from vacuum trucks, excavators, dump trucks, power generators, air compressors, paving equipment, concrete equipment, etc.).

    Moving in/out and Deliveries

    Efforts will be made to accommodate properties that have scheduled move-ins / move-outs and deliveries. Please contact the site inspector in advance to advise of any delivery access.

    Garbage and Recycling

    Please have materials placed at curbside before 7 a.m. on your collection day. If required, the contractor will move bins to an appropriate location and return them in reasonable amount of time. Please ensure that you label your bins with your address.

    Site Inspector

    If you have construction questions or an issue onsite we ask that you be directed to the site inspector who is onsite daily and wearing a white hardhat with either the City logo on it.

    Site Inspector - William Kinnaird (226-750-5122 or william.kinnaird@kitchener.ca)

    If the site inspector is unavailable, please contact the Project Manager listed below.

    Need more information?

    If you have questions about the upcoming work, please contact us.

    City Project Manager - Brent Garcia (519-503-1100 or brent.garcia@kitchener.ca)

    TTY Hearing Impaired Service 1-866-969-9994

    Engineering General inquiries 519-741-2426

    Thank you for your continued patience.

Page last updated: 23 May 2024, 03:14 PM