As part of the City of Kitchener’s ongoing efforts to provide consistent and reliable service, we have scheduled road and sewer improvements in your neighbourhood on the street(s) listed above.
These improvements are scheduled to begin
- Stage 1 – Wellington Street North (Patrick Street to Spring Valley Road)
- Start of construction – April 2026
- End of construction – November 2026
- Stage 2 – Wellington Street North (Lancaster Street West to Patrick Street)
- Start of construction – April 2027
- End of construction – November 2027
- Stage 3 – Patrick Street (Wellington Street North to End) and Johnston Street (Patrick Street to End)
- Start of construction – April 2028
- End of construction – November 2028
About the improvements
The following is a brief list of specific improvements being considered:
- Upgrade the existing storm sewer, sanitary sewer and water mains, including additional hydrants as required.
- Replace existing sanitary and water services from the new mains to the property line.
- Curb and gutter, and sidewalks will be installed.
- Asphalt Multi-Use Trail on the north side of Wellington Street North.
- Upgrade the asphalt roadway.
- Replace all driveway ramp entrances in concrete.
- Install and/or replace retaining walls.
These improvements are being done to upgrade the existing, deteriorated underground services and above-ground surface features, in order to prevent future system failure. The project will be funded through utility user fees and will not result in a direct charge to the homeowner.