Public information meeting follow-up

November 23, 2026

Thank you to everyone who attended the first public information meeting on October 27. The presentation material, drawings and information booklet provided at the meeting are now available in the key documents section of this project page.

Below is some additional information addressing common questions submitted at the meeting.

Access and Parking during construction

During working hours (typically 7a.m. to 5:30 p.m. but can go as late as 7p.m.) vehicle access in/out of driveways is generally not possible. During this time, sidewalks will be maintained to the extent possible as a route for pedestrians to move in and out.

Some vehicles access can be provided at certain times if resident needs are known in advance of the design process being completed.

Longwood Drive only has sidewalk on one side of the road, meaning residents without sidewalks need to be comfortable walking over the grass in their neighbours boulevards or crossing a potentially muddy street to the sidewalk to enter/exit the street.

Sometimes, the sidewalk or boulevard will be blocked in a certain location to replace water and sewer services to houses - in this case residents would either need to cross to the other side of the road or walk in the opposite direction.

Residents will be provided parking passes so that they can move their vehicles to nearby streets (e.g. Moccasin or Greenbrier). It is advised that if you need the use of your vehicle on any given day, you move it to the adjacent street prior to 7 a.m.

On most days during the construction project, driveway access will be available during the evening and on weekends. For those with mobility limitations, it’s advised to plan all your discretionary trips (e.g. grocery shopping, etc.) during this time. For those with recreational vehicles, please plan to move them during evenings or weekends. Please note that road conditions may not always be favourable, such as after a large rain event, so please keep an eye on the forecast.

If you have non-discretionary appointments (e.g. medical, meals on wheels, etc.) and are mobility limited, please contact the City’s project manager with the times so that arrangements can be made to provide access.

The majority of construction time is spent replacing underground services. Near the end of construction, when the concrete work begins (curb, sidewalk, driveway apron) there will be a number of days when driveway access is not possible. Concrete can be walked on the day after placement, but can’t be driven over for about three days. Moreover, concrete work doesn’t all happen in one day. Typically curb is placed on day 1, then sidewalk in the following days and driveway aprons after that. During this time, residents may not be able to enter their driveway but can drive on the road up to the front of their house. Unloading of mobility limited passengers and groceries can be done while temporarily parked on the road in front of your house. Then the car can be moved back to an adjacent street. In some situations the contractor may allow residents to parallel park on the street after curbs are installed, prior to asphalt being placed.

Phasing of the work to minimize access restrictions

Phasing of the project can minimize the amount of time the road is under construction in front of a given group of houses. As of now, phasing hasn’t been decided. Phasing typically works if there are logical break points in how infrastructure was installed that allow for phasing. These need to be assessed once the design is closer to completion.

Additionally, there are pros and cons to phasing. A pro is the work disrupts a smaller number of residents and maintains daytime access to more homes at any one time. The con is the entire project will typically take longer and result in more instances of everyone’s water being temporarily shutdown for extended periods. Water shutdowns extend beyond the area being worked on and will likely include residents on Moccasin and Greenbrier. Depending on the work and location of water valves, they could experience those extra water shutdowns as well.

As the design progresses, this will all be reviewed to determine the most appropriate approach.

Street Trees

Somewhat surprisingly, of all the comments regarding trees there were more requests to remove trees than preserve them, which is the opposite of most road reconstruction projects. Regardless, street trees are the domain of the City of Waterloo’s Forestry department and so the decision to remove trees is not strictly with the City’s project manager. The approach to street trees on road reconstruction projects can be summarized as follows:

  • The City’s project manager will note which trees are on top of underground services that need to be replaced.
  • The project manager will then assess whether the tree needs to be removed in order to open a trench to replace the underground services, or if there are any trenchless techniques available that can be used to replace the service and save the tree. Even when trenchless techniques are available they may not always be feasible for a variety of reasons.
  • Once a list of trees in need of removal is identified, the list is reviewed with the City of Waterloo’s Forestry department. Sometimes Forestry may request additional tree removals for dead or declining trees. Beyond this, no other trees will be removed as part of the project.