Construction begins April 2

The City of Kitchener will reconstruct the road on Patricia Avenue from Highland Road E to Queen’s Blvd in 2024 by completing this in two separate stages. The city’s hired contractor is Regional Sewer & Watermain Ltd will start Stage 3 work on/about April 2, 2024 with limits on Patricia Ave from Highland Road West to Queen’s Boulevard. Stage 4 will follow later in 2024.

This work is part of the Council-approved 2024 Capital Works Program to renew aging city roads, sanitary sewers, storm sewers, watermains, and sidewalk for current and future needs. Please see a map of the work area below. Impacts on properties are expected, including planned water shut-offs, excavation pits and limited parking. For the duration of the construction, affected properties will receive water via a temporary water supply system.

If you would like to receive updates for this project, please subscribe and you will be added to the email list. Add your email to the Stay Informed box on this page and click 'Subscribe'.

Map of work area

Map of work area, showing stage 3 between Highland and Spadina, and stage 4 between Spadina and Queen's



What to expect during construction

Work Hours

Work will take place from 7 a.m. to 7 p.m., Monday to Friday; work on weekends may also be required from time to time, but is unlikely, and is pre-approved Saturday and Sundays from 7 a.m. to 7 p.m..

Construction noise

You may experience intermittent noise and vibration during construction (from vacuum trucks, excavators, dump trucks, power generators, air compressors, paving equipment, concrete equipment, etc.).

On-Site Communication

There are times when contractors need to communicate with homeowners about what is happening on-site. This could be about driveway access, water shut-offs, pre-construction inspections, and site restoration work (landscaping, installing pavers etc.). Contractor's staff will be identifiable by their high-visibility company branded clothing. If you need to speak with staff on the construction site, please ask for the Site Inspector.

Accessible Accommodation

The City's contractor must ensure safe and accessible walkways and entryways are maintained for everyone during construction. Any temporary access disruptions will be communicated as soon as possible. If you experience a disruption, have a specific access need or related accommodation request, contact the person listed below.

Residents who require accommodation (level entry, longer notice, etc.) must contact the Project Manager to arrange for access during the construction period.

J F Carmichael Public School

For the safety of the public during construction, access to JF Carmichael Public School will be via either North Drive / Marlborough Avenue and/or Spadina Road West walkway. The contractor will be installing safety fencing along the frontage of the school on Patricia Avenue to help direct students, parents/guardians, and faculty/staff to enter/exit the school via the alternate routes. For your safety, we ask that you please always avoid the active construction site on Patricia Ave.

Please see a map of the work area below and alternate routes.

Site Inspector

If you have construction questions or an issue onsite, we ask that you be directed to the site inspector who is onsite daily and wearing a white hardhat with the City logo on it. If the site inspector is unavailable, please contact the Project Manager listed below.

Telephone and Internet Services

This work may affect phone and internet cables for individual properties that aren't buried deep below the sidewalk. The contractor will coordinate with utility companies to minimize disruption. Residents who find their service has been disrupted should notify their phone or internet service provider immediately to start the repair process.

Water service disruptions

The water to your property will need to be shut off to allow for connection and disconnection to the temporary water supply. The contractor will provide at least 48-hour advance notice for all planned shut-offs.

Throughout the work, it is recommended that you temporarily disconnect any water treatment systems (i.e., softeners or filters), water-cooled air conditioners or similar plumbing fixtures.

Automatic lawn sprinkler systems may also be affected; therefore, you may need to water manually. If you did not receive advance notice and your water was turned off, an emergency water shut-off may have been necessary to complete the work.

Important information for owners of sprinkler systems / heated driveways and private landscaping features

Property owners should remove items located within City property limits (boulevard) to avoid damage. This includes items such as landscaping (plants and pavers), decorative objects, sprinkler systems or heated driveways. If you have a sprinkler system or heated driveway, please contact the Project Manager listed below.

Road and Sidewalk Access

In order to complete the work in a safe manner, there will be road and sidewalk restrictions within the work zone. Access for emergency vehicles will be maintained at all times.

Driveway Access

The contractor will notify you of any temporary restrictions to your driveway access. There will be times where driveway access is not possible due to the nature of the work.

During reconstruction, temporary parking permits will be issued to displaced residents to allow on-street parking when needed. The permits will list streets for parking options as you will be permitted to park longer than 3 hours and overnight. Permits are to be displayed on the dash of your vehicle. Ensure that your vehicle is parked in permitted areas only and that you do not interfere with any construction operations. We communicate with the Bylaw Enforcement team to ensure residents displaced by construction are noted, although illegal parking and/or safety related issues will continue to be enforced.

Parking

This project will affect on-street parking. Parking in the active work zone is not permitted as space is needed for construction equipment and materials. If your parked vehicle affects construction work, it will be relocated with no charge to the owner.

If you require parking enforcement, please contact 519-741-2345.

Traffic Management

Efforts have been made to manage traffic in the area for the safety of workers, road users and residents. Road users should expect delays and increased traffic on nearby main and side streets.

Moving in/out and Deliveries

Efforts will be made to accommodate properties that have scheduled move-ins / move-outs and deliveries. Please contact the site inspector in advance to advise of any delivery access.

Garbage and Recycling

Please have materials placed at curbside before 7 a.m. on your collection day. If required, the contractor will move bins to an appropriate location and return them in reasonable amount of time. Please ensure that you label your bins with your address.

Restoration

The construction work area will be restored with sod, concrete and/or asphalt where required. Interlocking bricks, flagstone on a granular base, or other similar features that are removed from public and private property during construction will be replaced. Further information notice regarding sod will follow once the sod is placed.


Need more information?

If you have questions about the upcoming work, please contact us.

City Project Manager

Jeff Riedl

jeff.riedl@kitchener.ca

519-497-5917 (TTY:1-866-969-9994)

Engineering General inquiries

519-741-2426

Thank you for your continued patience.


Share Construction begins April 2 on Facebook Share Construction begins April 2 on Twitter Share Construction begins April 2 on Linkedin Email Construction begins April 2 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>