Construction Update - Fall 2024

27 November 2024

Hello Wilson Avenue Community!

As you may have seen, construction has been going well and there has been great progress with the interior and exterior work over the last few months, including:

  • Most of the building façade is complete
  • Installation of the roof
  • Installation of windows and doors for residential units
  • Completion of underground electrical work
  • Completion of exterior building link connection
  • Beginning of elevator installation

What to expect in the coming months?

Over the winter months the following work will take place:

  • Installation of the new elevator
  • Interior unit framing
  • Interior unit insulation and interior unit drywalling
  • Building façade finishes

Anticipated Construction Completion

The redevelopment of 84 Wilson Ave is on track to be completed and occupied by Summer 2025.

We would love to stay connected with you!

Please connect with us if you have any questions about the project:

Email: wrhredevelopments@regionofwaterloo.ca(External link)

Phone: 519-575-4400 ext. 6000

Regards,

The 82 Wilson Project Team