Construction update April 30, 2026

30 April 2026

Note: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change, and residents should be prepared for unexpected changes.

The current plan for construction over the two-week period from April 28 to May 12 is:

  • Continue commissioning temporary watermain for Phase 1A, and begin switching certain properties over to the temporary watermain.
  • Shutdown water in area in order to isolate the watermain in Phase 1A so that it can be replaced. Water shutdown will extend beyond the limits of work and residents and businesses will be provided notice by the contractor.
  • Replacement of sanitary and water services from property line to curb line.
  • Replace sanitary sewer.

A reminder that temporary changes to on-street parking in the neighbourhood has been enacted. Certain areas have had on-street parking removed to facilitate conversion of some streets to 2-way traffic or maintain space for emergency access during higher than average traffic volume. Please watch for street signs for the changes. Where signs prohibit parking, except with a valid permit, means those with parking passes provided to affected property owners at the start of construction are permitted to park.