Construction update August 7, 2026

August 7, 2026

Note: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can change quickly, and residents should be prepared for unexpected shifts.

Construction work between now and August 14 includes:

  • For Phase 1A (Willow to Herbert): Maintenance of roadway until asphalt is scheduled and final granular material is placed.
  • For Phase 1B (Herbert to Mary): Complete storm sewer and begin replacement of watermain and sanitary sewer