Construction update November 13, 2026

November 13, 2026

Note: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change, and residents should be prepared for unexpected changes.

Construction plans for the next two weeks include:

  • Thursday, November 12 – Hydro vacuum excavating two areas near the intersection of Union and Mary to correct a tracer wire issue. Possibly also installing conduit for new pedestrian crossover at Herbert Street.
  • Phase 1B and Phase 1C - Starting on November 13, concrete crews will begin forming and pouring sidewalk, then move on to forming and pouring concrete driveway aprons and concrete driveways following the weekend.
    • Sidewalks can be walked on the morning after they are poured, although not driven on for 72 hours.
    • On the day that a sidewalk is poured, residents will need to navigate this work by walking on the grass around newly poured concrete, stepping over form work, and walking along the gravel road.
  • Phase 1B and 1C - Asphalt paving of the roadway tentatively scheduled for November 23.
    • This time of year is extremely busy for paving sub-contractors.The date above could get pushed back due to weather, ormoved up if other work finishes early or there’s a cancellation.
  • Start topsoil and sodding would start following paving of roadway.