The current schedule for the next several weeks.

  • Final watermain connections on Thursday October 29, 2026 (re-scheduled from previous date). This is dependent on a successful commissioning process. Alternate date if needed, Monday November 2, 2026.
  • Concrete curbs, possibly as early as Friday October 30, 2026.
  • Remaining concrete sidewalk and driveway aprons following curb work (majority of the week of November 2, 2026.
  • Roadway granular material and asphalt once all other concrete work is completed.

Once concrete work starts, affected residents may not have driveway access, even during the evening or on weekends, for an extended period. Please plan accordingly.