Construction update April 30, 2026

30 April 2026

Note: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change, and residents should be prepared for unexpected changes.

The current plan for construction over the two-week period from April 28 to May 12 is:

  • Continue with concurrent replacement of sanitary sewer and watermain, and associated service laterals, for Phase 1.
  • Start installation of new storm sewer for Phase 1.
  • Excavate and replace granular road base for Phase 1.
  • Possible, depending on progress: Begin removals for Phase 2.

At the current time the intersection of Roger St. and Moore Ave. is open during working hours. Once the contractor begins work on Phase 2, which may happen at the end of the two week period, depending on the pace of progress. Once this happens, the intersection will be shut down entirely for a time. Please be aware that this is coming up and plan accordingly.