Construction update August 18, 2026

August 19, 2026

Note: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change, and residents should be prepared for unexpected changes.

The current plan for construction between now and August 28 is:

  • Adjust lids/grates on storm and sanitary structures.
  • Prepare driveways for paving.
  • Asphalt paving of road and driveways.
  • Abandon sanitary forcemain in boulevard on Moore Ave from Graham St to just south of Guelph St.
  • Start installation of signage and line painting.