Construction update July 7, 2026

July 9, 2026

Note: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change, and residents should be prepared for unexpected changes.

The current plan for construction between now and July 24 is:

  • Continue installation of new storm sewer.
  • Abandon sanitary pump station and force main in boulevard along Moore Ave S.
  • Testing and commissioning of new watermain between Roger St and Peltz Ave.
  • Connection of new watermain to broader system (will involve water shutdown).
  • Excavation of road and placement of the roadways granular base and subbase.