Construction update November 13, 2026

November 13, 2026

Note: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change, and residents should be prepared for unexpected changes.

Work over the next two weeks will primarily be completed together with similar activities on Union Street and shouldn’t require any road closures, but may involve drivers to drive around temporary work zones or yield to opposing traffic. The following lists work yet to be complete:

  • Complete remaining concrete work to fill in gaps in sidewalk due to pump station abandonment work.
  • Complete landscape restoration of areas where signs were located, where the site office was located and elsewhere.
  • Complete hydraulic sewer cleaning and deflection testing, pending completion of benching and parging of sewer structures.
  • Install new “no parking” signage between Waterloo and Graham St.
  • Complete CCTV inspection of new sewers, following hydraulic cleaning and deflection testing.