Construction update September 18, 2026

September 18, 2026

Note: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change, and residents should be prepared for unexpected changes.

Despite the roadway being paved, the project is not yet complete. Please be mindful that on-going activities will be continuing and may, on short notice, lead to a lack of access during the workday.

The current plan for construction between now and October 2, 2026 is:

  • Finish coating the inside of storm and sanitary structures.
  • Complete sewer cleaning.
  • Install new “no parking” signage between Waterloo and Graham Streets.
  • Finish in-place abandonment of sanitary forcemain in boulevard on Moore Ave. from Graham St. to just south of Guelph St. Process has begun, but is not yet complete.