Construction update September 8, 2026

September 8, 2026

Note: Construction updates are being provided as a courtesy to keep residents appraised of upcoming work. Due to the nature of construction, schedules can quickly change, and residents should be prepared for unexpected changes.

Despite the roadway being paved, the project is not yet complete. Please be mindful that on-going activities will be continuing and may, on short notice, lead to a lack of access during the work day.

The current plan for construction between now and September 15, 2026 is:

  • Abandon sanitary forcemain in boulevard on Moore Ave from Graham St to just south of Guelph St.
  • Start installation of signage and line painting.
  • Sewer cleaning and CCTV inspection.
  • Misc cleanup.